Review article

Calculation of the parameters of the streamline work organization by the critical path method

UDC: 

658.512.6:658.527:69

DOI: 

10.23968/1999-5571-2018-15-3-90-97

Pages: 

90-97

Annotation: 

In order to solve the problems of work organization optimization, cutting the duration of project construction and reducing downtimes, the models of the streamline work organization and network models are used. The article shows the unified character of various streamline methods and the network planning method known as the critical path method. The author presents an algorithm for calculating the streams with continuous development of the operation field by the critical path method. This algorithm may be of interest for specialists engaged in scheduling of the terms of work using modern project management software programs.

Authors: 

Bovteev S. V. Saint Petersburg State University of Architecture and Civil Engineering

Links to authors' articles: 

Journal Issue